This is our work so far
First hours - Lay the foundations and mark out land space and plan for work to start.
http://i1090.photobucket.com/albums/i378/Pong_Lenis/Screenshot_2011322_19_38_15.jpg
Day 1-2 - We cleaned out the junk piles and planned for the Fortress.
http://i1090.photobucket.com/albums/i378/Pong_Lenis/Screenshot_2011321_3_17_58.jpg
Day 3 - We started the work on our outer walls.
http://i1090.photobucket.com/albums/i378/Pong_Lenis/Screenshot_2011325_2_21_46.jpg
Day 4 - Work continues on our walls.
http://i1090.photobucket.com/albums/i378/Pong_Lenis/Screenshot_2011325_2_23_8.jpg
Day 5 - Still working on our walls clear another junk pile to create room.
http://i1090.photobucket.com/albums/i378/Pong_Lenis/Screenshot_2011325_2_25_43.jpg
Day 6 - Work on the south wall and linking it round to the west wall.
http://i1090.photobucket.com/albums/i378/Pong_Lenis/Screenshot_2011326_17_53_40.jpg
Day 7 - Gate house designed and put in place leveling of floors and building of bricks.
http://i1090.photobucket.com/albums/i378/Pong_Lenis/Screenshot_2011327_15_5_29.jpg
We currently are now waiting to level land clear junk piles and fill in walls with bricks.
First hours - Lay the foundations and mark out land space and plan for work to start.
http://i1090.photobucket.com/albums/i378/Pong_Lenis/Screenshot_2011322_19_38_15.jpg
Day 1-2 - We cleaned out the junk piles and planned for the Fortress.
http://i1090.photobucket.com/albums/i378/Pong_Lenis/Screenshot_2011321_3_17_58.jpg
Day 3 - We started the work on our outer walls.
http://i1090.photobucket.com/albums/i378/Pong_Lenis/Screenshot_2011325_2_21_46.jpg
Day 4 - Work continues on our walls.
http://i1090.photobucket.com/albums/i378/Pong_Lenis/Screenshot_2011325_2_23_8.jpg
Day 5 - Still working on our walls clear another junk pile to create room.
http://i1090.photobucket.com/albums/i378/Pong_Lenis/Screenshot_2011325_2_25_43.jpg
Day 6 - Work on the south wall and linking it round to the west wall.
http://i1090.photobucket.com/albums/i378/Pong_Lenis/Screenshot_2011326_17_53_40.jpg
Day 7 - Gate house designed and put in place leveling of floors and building of bricks.
http://i1090.photobucket.com/albums/i378/Pong_Lenis/Screenshot_2011327_15_5_29.jpg
We currently are now waiting to level land clear junk piles and fill in walls with bricks.